dc.coverage.spatialStudy on influence of resource Constraints in time overrun of Construction projectsen_US
dc.date.accessioned2015-05-20T08:23:38Z-
dc.date.available2015-05-20T08:23:38Z-
dc.date.issued2015-05-20-
dc.identifier.urihttp://hdl.handle.net/10603/41930-
dc.description.abstractThe construction industry plays a major role in the development of newlineIndian economy This industry consumes about 65 percent of the eleventh newlineyear plan outlay and contributes nearly 11 per cent of the GDP However newlinethe performance record in successfully implementing infrastructure projects in newlineIndia has not been very encouraging Most of the construction projects in newlineIndia are exposed to time overrun This phenomenon may affect the progress newlineof the construction industry in India as well as cause many organizations of newlineconstruction to be destroyed newlineThis study focuses on the identification and evaluation of factors newlineaffecting the time overrun in the Indian construction projects The objectives newlineof the study were achieved through two approaches the first one was a mixed newlineapproach of interviews structured questionnaire surveys and case studies and newlinethe second one was development of the time overrun model An all India newlinequestionnaire survey has been administered among three major participants in newlineGovernment public and private projects One hundred and fifty five newlinequestionnaires were administered through personal contact to public and newlineprivate organizations newlineThe survey responses were statistically analyzed The Relative newlineImportant Index RII was used to rank the significant factors causing time newlineoverrun in construction projects in India newline newlineen_US
dc.format.extentxxi, 182p.en_US
dc.languageEnglishen_US
dc.relationp174-180.en_US
dc.rightsuniversityen_US
dc.titleStudy on influence of resource Constraints in time overrun of Construction projectsen_US
dc.title.alternativeen_US
dc.creator.researcherVenkatesh M Pen_US
dc.subject.keywordGovernment publicen_US
dc.subject.keywordRelative Important Indexen_US
dc.description.noteappendix p153-173, reference p174-180.en_US
dc.contributor.guideUmarani Cen_US
dc.publisher.placeChennaien_US
dc.publisher.universityAnna Universityen_US
dc.publisher.institutionFaculty of Civil Engineeringen_US
dc.date.registeredn.d,en_US
dc.date.completed01/06/2014en_US
dc.date.awarded30/06/2014en_US
dc.format.dimensions23cm.en_US
dc.format.accompanyingmaterialNoneen_US
dc.source.universityUniversityen_US
dc.type.degreePh.D.en_US
Appears in Departments:Faculty of Civil Engineering

Files in This Item:
File Description SizeFormat 
01_title.pdfAttached File23.95 kBAdobe PDFView/Open
02_certificate.pdf103.77 kBAdobe PDFView/Open
03_abstract.pdf14.43 kBAdobe PDFView/Open
04_acknowledgement.pdf8.38 kBAdobe PDFView/Open
05_content.pdf67.65 kBAdobe PDFView/Open
06_chapter1.pdf119.25 kBAdobe PDFView/Open
07_chapter2.pdf175.27 kBAdobe PDFView/Open
08_chapter3.pdf330.71 kBAdobe PDFView/Open
09_chapter4.pdf126.03 kBAdobe PDFView/Open
10_chapter5.pdf257.92 kBAdobe PDFView/Open
11_chapter6.pdf332.69 kBAdobe PDFView/Open
12_chapter7.pdf27.5 kBAdobe PDFView/Open
13_chapter8.pdf63.52 kBAdobe PDFView/Open
14_appendix.pdf110.04 kBAdobe PDFView/Open
15_reference.pdf300.55 kBAdobe PDFView/Open
16_publication.pdf43.84 kBAdobe PDFView/Open


Items in Shodhganga are licensed under Creative Commons Licence Attribution-NonCommercial-ShareAlike 4.0 International (CC BY-NC-SA 4.0).

Altmetric Badge: